Project |
Umran – Sana'a – Dhamar – Ta'iz – Aden
Road |
|
Total Cost |
SR. 7313.00 million |
|
SFD’s Contribution |
SR. 400.00 million |
|
Date Agreement Signed |
05/04/2009 |
|
Estimated Completion Date |
End of 2015 |
|
Executing Agency |
The Ministry of Public Works and Highways |
|
 |
|
Project
Description and Objectives:
The project aims at developing the land transportation network and urban and
rural areas in Yemen. This project shall be a road lined with the existing road
with a width of 13.45 m for each lane in addition to a central median of 3.6 m
width and shoulders on both sides of 3.6 m width for each lane. The total length
of the road is 420 km distributed into 4 sections. The project includes the
following components:
a. Civil works that include the filling and asphalt works and the
concrete construction works for the following sections:
First section: Umran – Sana,a with a length
of 68 km.
Second section: Sana,a – Dhamar – Beit
Al-Komani with a length of 95 km.
Third section: Beit Al-Komani – Ibb – Ta`iz
with a length of 117 km.
Fourth section: Ta`iz – Al-Houta- Aden with
a length of 140 km.
b. Possession of lands.
c. Engineering supervision services. |
|