Project                 : Taschort Dam

Total Cost

:

SR 223.00 million

SFD’s Contribution

:

SR 100.00 million

Date agreement Signed

:

18/05/2007

Estimated Completion Date

:

End of 2010

Executing Agency

:

Directorate of Water supplies, Ministry of National Soil, Water and Environment

 Project Description and Objectives :

     The project's objective is to construct a reinforced concrete dam on Asif Almal valley in the Shishawa region. The dam's storage capacity is of about 25 million cubic meters. The dam’s height from the base level is 75 meters. The length is 450 meters in the top and 66 meters in the base. The dam’s lake is estimated to be 10 kilometers length, and 1.5-2 kilometers width. The project consists of the following sections :
1 - Expropriation .
2 - Preparation works .
3 - Construction works .
4 - Hydro-mechanical works .
5 - Studies and Supervision .