    Nepal

 

 

Project                 : Completion of Bagmati Irrigation Project

Total Cost

:

SR. 212.66 million

SFD’s Contribution

: SR. 56.25 million

Date agreement Signed

:

03/09/2007

Estimated Completion Date

: Mid July 2012

Executing Agency

: Ministry of Water Resources, Irrigation Department

 Project Description and Objectives :

     The project's objective is to complete the land reclamation and the infrastructure of the irrigation system in the target areas of 68,000 hectares in the regions of Searlahi, Ruteat and Parra. The project is of two phases :
    Phase I: completion of agricultural land reclamation and infrastructure for the irrigation system for an area of 16600 hectares out of the remaining targeted region of 45,600 hectares in the Searlahi and Ruteat regions, in addition to rehabilitate Bagmati irrigation system.
   
Phase II: Execution of the infrastructure of the irrigation system and agricultural land reclamation in the Parra region for an area of 22,400 hectares .